This examination consists of two sections.
Section A - Twenty short answer questions worth three marks each. Candidates must answer ALL TWENTY questions. It is recommended that candidates allow approximately one hour for this section.
Section B—Six structured questions worth 15 marks each. Candidates must answer ALL SIX questions. It is recommended that candidates allow approximately 11/2 hours for this section.
Section A - Answer ALL
TWENTY questions in this section.
|
1 |
An
installation has been seriously overloaded and needs investigation. State
the |
|
|
|
|
a) |
type
of inspection and test that would be required |
(1 mark) |
|
|
b) |
certificate
that will need to be completed |
(1 mark) |
|
|
c) |
documentation
that must accompany the certificate in b) |
(1 mark) |
|
2 |
State
the |
|
|
|
|
a) |
statutory
document that is relevant to electrical systems |
(1 mark) |
|
|
b) |
non-statutory
document that details the use of electrical test equipment |
|
|
|
c) |
non-statutory
document that sets out the requirements for electrical installations |
|
|
3 |
State
who |
|
|
|
|
a) |
should
decide when the first periodic test on an installation should be carried
out |
|
|
|
b) |
should
decide when further periodic tests on an installation should be carried
out |
|
|
|
c) |
the
extent and limitations of a periodic inspection and test should be agreed
with. |
|
|
4 |
State
the form of shock protection offered by the following |
|
|
|
|
a) |
placing
out of reach |
(1 mark) |
|
|
b) |
EEBADS |
(1 mark) |
|
|
c) |
class
II equipment |
(1 mark) |
|
5 |
State
the instruments required for the following tests |
|
|
|
|
a) |
continuity
of ring final circuit conductors |
(1 mark) |
|
|
b) |
insulation
resistance |
(1 mark) |
|
|
c) |
live
polarity |
(1 mark) |
|
6 |
State,
apart from loose connections, three circumstances that would result
in an increase in conductor resistance |
|
|
7 |
The
c.p.c. continuity of a radial circuit comprising four socket outlets is to
be tested. If the test method uses a temporary link between phase and
earth in the distribution board, state |
|
|
|
|
a) |
at
which points in the circuit the test should be conducted |
(1 mark) |
|
|
b) |
the
conductors between which the test should be made |
(1 mark) |
|
|
c) |
the
significance of the reading at the farthest point |
(1 mark) |
|
8 |
State
THREE wiring systems that would not normally require a separate
thermoplastic (p.v.c.) insulated conductor as a CPC |
|
|
9 |
For
a ring final circuit, state |
|
|
|
|
a) |
why
the test between P and N is conducted |
(1 mark) |
|
|
b) |
the
reason why phase to neutral readings at each socket would increase towards
the mid point of the ring then decrease again |
(1 mark) |
|
|
c) |
the
other test that is automatically conducted |
(1 mark) |
|
10 |
For
the insulation resistance test on a 230 V installation, state the |
|
|
|
|
a) |
test
voltage to be applied |
(1 mark) |
|
|
b) |
minimum
value of resistance acceptable |
(1 mark) |
|
|
c) |
value
below which further investigation is required |
(1 mark) |
|
11 |
The
insulation resistance of 600 V discharge lighting installation is to be
tested, state the |
|
|
|
|
a) |
test
instrument to be used |
(1 mark) |
|
|
b) |
test
voltage to be applied |
(1 mark) |
|
|
c) |
minimum
value of insulation resistance |
(1 mark) |
|
12 |
For
an installation in a bathroom, state the |
|
|
|
|
a) |
type
of socket outlet permitted, excluding shaver sockets |
(1 mark) |
|
|
b) |
location
of zone 0 |
(1 mark) |
|
|
c) |
rating
of an r.c.d. protecting an item of equipment in zone 1 |
(1 mark) |
|
13 |
To
what IP codes should the following comply? |
|
|
|
|
a) |
Accessible
horizontal top surfaces of enclosures. |
(1 mark) |
|
|
b) |
An
intermediate barrier inside an enclosure |
(2 marks) |
|
14 |
For
the testing of polarity, state why |
|
|
|
|
a) |
single
pole devices should be in the phase conductor only |
(1 mark) |
|
|
b) |
certain
modern E14 and E27 lamholders do not require testing |
(1 mark) |
|
|
c) |
a
live polarity test is required |
(1 mark) |
|
15 |
The
total loop impedance of a circuit may be calculated using the following
fomula
|
|
|
|
|
a) |
Ze |
(1 mark) |
|
|
b) |
R2 |
(1 mark) |
|
|
c) |
1.2 |
(1 mark) |
|
16 |
State
the |
|
|
|
|
a) |
important
check to be made regarding equipotential bonding carrying out a loop
impedance test on a circuit |
|
|
|
b) |
action
to be taken regarding the earthing conductor prior to conducting an
external loop impedance test |
|
|
|
c) |
precaution
that should be taken before conduction the test in b). |
(1 mark) |
|
17 |
A
test is to be conducted on a lighting conductor earth electrode. State the |
|
|
|
|
a) |
instrument
to be used |
(1 mark) |
|
|
b) |
other
two electrodes used in the test |
(2 marks) |
|
18 |
State
three circumstances under which an r.c.d. having an operating
current of 30 mA, or less, must be used in an installation |
|
|
19 |
State |
|
|
|
|
a) |
why
a test on an r.c.d. must not be conducted before a loop impedance test |
|
|
|
b) |
the
reason for a functional test on an r.c.d. |
(1 mark) |
|
|
c) |
the
maximum test current that needs to be applied to a 100mA r.c.d. |
(1 mark) |
|
20 |
A
single-phase T.N.C-S installation has a measured value of external loop
impedance of 0.015 ohms. Show by calculation the expected value of the
prospective fault current. |
|
Section
B Questions 21 to
26 refer to the following scenario. Answer ALL SIX questions. All questions carry
equal marks.
A
15-year-old dry-powder coating factory is situated adjacent to an 11kV/415/240V
Regional Electricity Company substation. The earthing system is T.N-C-S with an
external earth fault loop impedance (Ze) of 0.012Ω and a prospective fault
current of 20 kA.
The
dry-powder coating process involves cleaning metallic components in an acid
bath, washing off with water sprays, drying with hot air blowers, spraying with
electrostatically charged powder and finally baking in a tunnel oven.
The
existing installation, which are all radial circuits, is wired with (p.v.c.)
conductors in metal conduit and trunking. Six new lighting circuits supplying
high-bay 300W SON luminaires have been installed using a similar wiring system
to the existing installation. The new circuit breakers are fed from a metal clad
distribution board housing BS EN 60898 circuit breakers.
An
inspection and test of the whole installation is to be carried out.
|
21 |
State |
|
|
|
|
a) |
the
type/s of overall inspection and test required |
(4 marks) |
|
|
b) |
the
certification/documentation that needs to be completed by the inspector |
|
|
|
c) |
who
should receive the originals of these documents |
(1 mark) |
|
|
d) |
who
decides when the first periodic test should be conducted on the new
lighting |
|
|
|
e) |
One statutory and two
non-statutory documents relevant to this inspection and testing process |
|
|
|
f) |
the
status of the inspector |
(2 marks) |
|
22 |
State |
|
|
|
|
a) |
apart
from wear, tear and safety, five installation conditions that would
need to be considered during the inspection process |
|
|
|
b) |
Five items from the BS 7671
schedule of inspections that would need to be considered |
|
|
|
c) |
Three
human senses that would be used in the inspection process |
(3
marks) |
|
|
d) |
with
whom the extent and limitations of an inspection should be agreed |
|
|
23 |
List |
|
|
|
|
a) |
the
first four relevant tests, in sequence, to be conducted on the new
lighting installation |
|
|
|
b) |
All
relevant test equipment needed for a) |
(8
marks) |
|
24 |
a) |
Describe
how an Insulation Resistance test would be carried out on the new lighting
circuits |
|
|
|
b) |
If
an Insulation Resistance test between live conductors and earth on the
whole installation resulted in a test value of 1.6Ω, explain, giving
reasons, any actions to be taken. |
|
|
|
c) |
Describe
how an external loop impedance test should be conducted. |
(4
marks) |
|
|
d) |
Describe
how a prospective fault current test should be conducted at the origin of
the installation |
|
|
25 |
The
Maximum and measured values of loop impedance for four circuits are as
follows
|
|
||||||||||||||||
|
|
a) |
Explain
the reasons for the use of the ‘rule of thumb’ |
(3 marks) |
|||||||||||||||
|
|
b) |
Using
the above method, determine if the measured values are acceptable. (Show
all calculations). |
|
|||||||||||||||
|
|
c) |
For
any circuit that fails to comply, indicate two methods of
overcoming the problem. |
|
|||||||||||||||
|
26 |
a) |
Draw
a labeled diagram of the earth fault loop path for any circuit in the
installation. |
|
|
|
b) |
Explain
why it would be appropriate to use BS 3036 fuses in a distribution board
at the origin of this installation |
|
|
|
c) |
Most
standard PSCC testers are designed for single-phase use. How could an
appropriate value of short circuit current between phases be determined? |
|