This examination consists of two sections.
Section A - Twenty short answer questions worth three marks each. Candidates must answer ALL TWENTY questions. It is recommended that candidates allow approximately one hour for this section.
Section B—Six structured questions worth 15 marks each. Candidates must answer ALL SIX questions. It is recommended that candidates allow approximately 11/2 hours for this section.
Section A - Answer ALL TWENTY questions in
this section.
|
1 |
Three
single sockets have been added to a ring final circuit. State the. |
|
|
|
|
a) |
inspection
and test certificate that will need to be completed |
(1 mark) |
|
|
b) |
title
in law given to the inspector |
(1 mark) |
|
|
c) |
legal
status of the inspector |
(1 mark) |
|
2 |
An
engineering works is 18 years old and is due for inspection and test.
State the |
|
|
|
|
a) |
type
of inspection and test required |
(1 mark) |
|
|
b) |
documents
that must accompany the completed certificate |
(1 mark) |
|
|
c) |
circumstances
under which the type of inspection and test in a) above may not be
required. |
(1 mark) |
|
3 |
State
the legal status of the following |
|
|
|
|
a) |
BS
7671 2001 |
(1 mark) |
|
|
b) |
Guidance
Note 3 |
(1 mark) |
|
|
c) |
HSE
GS38 |
(1 mark) |
|
4 |
Give
ONE example of EACH of the following |
|
|
|
|
a) |
an
exposed conductive part |
(1 mark) |
|
|
b) |
an
extraneous conductive part |
(1 mark) |
|
|
c) |
direct
contact |
(1 mark) |
|
5 |
State
THREE methods of protection against indirect contact |
(3 marks) |
|
6 |
State
the earthing systems that use the following as return earth paths |
|
|
|
|
a) |
PEN
conductor |
(1 mark) |
|
|
b) |
cable
sheath |
(1 mark) |
|
|
c) |
general
mass of earth |
(1 mark) |
|
7 |
State
the test instruments to be used for the following tests |
|
|
|
|
a) |
continuity
of supplementary bonding in a bathroom |
(1 mark) |
|
|
b) |
external
earth fault loop impedance of a TN-C-S system |
(1 mark) |
|
|
c) |
live
polarity |
(1 mark) |
|
8 |
Give
THREE examples of notices/warning labels that should be present in an
electrical installation |
|
|
9 |
State
the IP code that applies to the following enclosures |
|
|
|
|
a) |
accessible
horizontal top surfaces |
(1 mark) |
|
|
b) |
internal
intermediate barriers |
(2 marks) |
|
10 |
The continuity of a lighting
circuit c.p.c. is verified using the phase conductor as part of the test.
State the |
|
|
|
|
a) |
instrument to be used |
(1
mark) |
|
|
b) |
action to be taken regarding the
test leads |
(1
mark) |
|
|
c) |
significance of the reading at the
furthest point |
(1
mark) |
|
11 |
State THREE outcomes
of the ring final circuit continuity test. |
(3
marks) |
|
12 |
State
the test voltage and minimum value of insulation resistance for EACH of
the following |
|
|
|
|
a) |
12V
fan circuit in a bathroom |
(1 mark) |
|
|
b) |
three-phase
commercial installation |
(1 mark) |
|
|
c) |
800V
discharge lighting circuit |
(1 mark) |
|
13 |
Give
THREE reasons for carrying out a polarity test on an installation, as
required by BS7671 2001 |
|
|
14 |
The
resistance of an earth electrode is to measured. If a mains supply is
unavailable, state the |
|
|
|
|
a) |
instrument
to be used |
(1 mark) |
|
|
b) |
terms
used to describe the TWO other test electrodes. |
(2 marks) |
|
15 |
State
the maximum disconnection times appropriate to the following |
|
|
|
|
a) |
a
domestic socket outlet circuit |
(1 mark) |
|
|
b) |
site
hut lighting on a construction site |
(1 mark) |
|
|
c) |
110V
reduced low-voltage system. |
(1 mark) |
|
16 |
State |
|
|
|
|
a) |
why
it may not be possible to obtain a measured value of loop impedance for a
circuit protected by an RCD |
|
|
|
b) |
how
this value may be determined without the use of a special instrument |
|
|
17 |
A
loop impedance test is to be conducted on a radial socket outlet circuit.
State |
|
|
|
|
a) |
where
in the circuit the test should be made |
(1 mark) |
|
|
b) |
TWO
conditions that may affect the validity of the measured value as a
comparison to the maximum value |
|
|
18 |
State
THREE reasons for the use of a 20mA RCD. |
(3 marks) |
|
19 |
In
the formula IΔ n = 50/Zs state |
|
|
|
|
a) |
what
is represented by ‘50’ |
(1 mark) |
|
|
b) |
the
maximum residual current rating of the RCD required, when the value of Zs
is 500Ω |
|
|
20 |
The
PFC at the origin of an installation is to be measured. State the |
|
|
|
|
a) |
instrument
to be used |
(1 mark) |
|
|
b) |
measurement
units |
(1 mark) |
|
|
c) |
importance
of the breaking capacity of the protective devices at the origin |
|
Section
B – Answer ALL SIX questions
Questions
21 to 26 all refer to the following scenario and Fig. 1 (attached).
Fig.1 shows the main intake and
circuit arrangements for the new electrical installation in a refurbished
dentist’s surgery. The heating,
ventilating and air-conditioning unit (HVAC), located outside the building is
supplied using p.c.v./p.c.v./s.w.a. multicore cable. All other circuits are
wired using p.v.c. single-core cables enclosed in concealed p.v.c. conduit and
surface trunking (c.p.c’s are the same size as the phase conductors). The
lighting is a mixture of tungsten filament, fluorescent and PIR-controlled
exterior security lights. The installation has been completed and is ready for
inspection and testing.
|
21 |
State
the |
|
|
|
|
a) |
type
of inspection and test to be completed |
(1 mark) |
|
|
b) |
certificate
that will need to be completed |
(2 marks) |
|
|
c) |
signatures
that are required on the certificate in b) |
(3 marks) |
|
|
d) |
status
of the signatories |
(2 marks) |
|
|
e) |
documents
that must accompany the certificate in b) |
(2 marks) |
|
|
f) |
information
regarding the incoming supply that should be recorded on ONE of the
documents in e) |
|
|
|
g) |
person
who should keep the original completed documents |
(2 marks) |
|
22 |
State |
|
|||||||||
|
|
a) |
the
terms used to describe EACH of the following items labelled
|
|
||||||||
|
|
b) |
the
earthing system |
(1 mark) |
||||||||
|
|
c) |
where,
on the gas and water supplies, item 2 should be connected |
(2 marks) |
||||||||
|
|
d) |
the
label that should appear at the connection in c) |
(1 mark) |
||||||||
|
|
e) |
why
a type D circuit breaker is used on B9 |
(3 marks) |
||||||||
|
|
f) |
FOUR
relevant items to be considered from the BS7671 2001 installation schedule |
(4 marks) |
||||||||
|
23 |
List,
in the correct sequence, the relevant tests to be carried out on the
installation circuits, indication the instruments to be used for EACH
test. |
(15 marks) |
|
24 |
Describe
how |
|
|
|
|
a) |
an
insulation resistance test would be carried out on circuit R1 |
(8 marks) |
|
|
b) |
a
c.p.c. continuity test would be carried out on circuit Y5 |
(7 marks) |
|
25 |
a) |
The
insulation resistance values for circuits R2, B6 and B9 were 3.8MΩ,
4.9Ω and 5.0MΩ respectively. All other circuits were in excess
of 999MΩ. Calculate the
approximate value of the overall insulation at the origin |
(7 marks) |
||||||||
|
|
b) |
When
the system is energised and before the sequence of live tests is
conducted, it is important to carry out a live polarity test. State
|
|
|
26 |
The
measured values of earth loop impedance for each circuit are as follows:
|
||||||||||||||||||||||||
|
|
a) |
State
the environment and circuit conditions which may have an effect on these
measured values
|
|
||||||||||||||||||||||
|
|
b) |
State
how these conditions are compensated for. |
(1 mark) |
||||||||||||||||||||||
|
|
c) |
Show,
by calculation, if the measured values are acceptable |
(5 marks) |
||||||||||||||||||||||
|
|
d) |
State
a solution for any circuit that fails to comply. |
(5 marks) |
||||||||||||||||||||||
Fig 1
